Every decision you have not made will be made for you

This is the whole problem in one sentence. A build generates decisions continuously, and it cannot wait. If the answer is not on a drawing and you are not reachable, the decision gets made by whoever is holding the trowel - at the speed the schedule demands, and usually in favour of the option that is easiest that morning.

None of that is bad faith. It is what happens when a question meets a deadline and no answer is available.

Documentation is remote control

The distance between "beautiful views" and "a house you can build without me" is a complete drawing set. Renders are not documentation. What you need on site is plans and sections, construction details, electrical and lighting layouts, a finishes schedule, and joinery drawn to the millimetre.

The thickness of your drawing set is the proportion of the house you have already decided.

This is also the cheapest place in the whole project to spend money. Every decision resolved on paper costs a fraction of the same decision resolved in concrete.

Decide in batches, ahead of the site

Work out with your architect what has to be decided before each stage, and decide it early:

Someone has to represent you on site

The contractor’s job is to build. Checking that what is built matches what you approved is a separate job, and it needs to be independent of the person being checked. That is what supervision is, and if you are abroad it is not optional.

What to insist on, whoever does it: an agreed visit frequency, written reports, photographs, and deviations raised with you before they are covered up rather than explained afterwards.

Photograph everything before it disappears

Ask specifically for photos of the things that are about to be hidden forever: waterproofing, insulation, services inside walls, drainage before backfill, structural connections before they are clad. A photograph taken the day before a wall closes is worth more than any amount of discussion the following spring.

Money follows work, never leads it

Pay against completed, verified stages. Keep a retention until the defects at handover are actually closed. An owner who has paid ahead of the work has lost the only leverage that reliably fixes problems.

The two visits worth flying for

What this looks like when it works

Owners who live abroad and end up happy tend to have the same three things: a complete set of drawings made before the first truck arrived, one point of contact who is accountable for what happens on site, and a decision calendar they stayed ahead of. Not a plane ticket every month.

That is how we are set up to work - the architects who drew the project are the ones who check it, which is also where a good part of the budget is protected.

Have a Property in Mind?

Send the location and what you want to do with it. You get a fixed fee and a realistic schedule before you commit to anything.

    Leave an email or a phone number - whichever suits you.

    We use these details only to reply to you. More in our privacy policy.